InSite SiteWork - Utilities

Confident estimating requires precise Take-off. Terrain-Link Trenches™ provide accurate excavation and backfill quantities based on changing ditch depths, using either earthwork contours from your site takeoffs or directly from digitized profiles.

Many general estimating programs contain "pipe" or utility modules for calculating trench excavation. First a typical ditch cross section is entered, next a pipe length is either entered or traced with a digitizer, and finally the volumes are calculated. This type of calculation is fine for utilities that remain at an even depth below grade, such as water or conduit. Of course these are fairly easy calculations, even when calculating using manual methods. 

runtype.jpg (7984 bytes)Sanitary and Storm drainage systems are much more difficult to calculate, as the pipe runs from structure to structure in a straight line, while the trench depth varies with the terrain. Here's where InSite's Terrain Link Trenching excels.

If you have entered soil borings, your excavation quantities are listed by strata. No other software has this capability at any price! Follow along as a utility take-off in InSite SiteWork is done step by step. 

TDS's

Utility Take-offs can be done by using the earthwork take-off to general profiles, or by tracing the profiles. Either way, the first step is to create a library of Typical Ditch Cross Sections (TDS's).

 Click here for Larger Version!

The TDS describes the excavation shape (including OSHA maximum vertical side height and layback slope), pipe dimensions, and top and bottom backfill thickness.

Layout

The next step is to locate the structures. Since InSite will use the earthwork take-off data to create utility profiles, the earthwork subgrade data has been displayed for clarity.

Click Image for High Resolution version!

 Information is then entered for each structure.

and each pipe run, including the invert elevations at the end of each pipe

If only one invert is known, a slope (percent) can be entered, and InSite will calculate the unknown invert.

Once the structure and pipe data has been entered, it's time to calculate the results. A series of cross sections are taken down the trench, at user selectable intervals. InSite uses the earthwork data to generate profiles, and calculates the results. As the calculations are made, a schematic showing the trench depths (cut brackets) are shown. 

The RockAlert™ feature is used to give an indication of a specific strata.  

For clarity on the illustration below, the zoom tools were used to focus on the utilities on the lower right portion of the site. Click on the image to see the complete utility take-off.

Click for High Resolution Version!

To View a profile, select Display/Edit profile from the pipe menu, and click on the first and last structure of the desired profile.

Click for High Res Version!

The profile, showing all the structures, connected pipes, and underground strata layers can be displayed. Profiles can also be printed or plotted at scale.

Once the utilities have been entered, InSite SiteWork gives complete reports.

Utility Summary Includes:     Click Here for Section Utility Summary

  1. Total Excavation for the entire utility take-off including the structure excavation. Includes breakdown by strata for take-offs with borings.
  2. Cut Bracket Quantities. Lists the linear feet of excavation in a depth range set by the estimator.
  3. Backfill Materials Quantities. Total of all backfill materials for both pipe and structures.

Pipe Report Includes:     Click Here for Pipe Report

Total Excavation, Cut Bracket Quantities, and Backfill Material Quantities for each individual pipe type (example 8" pipe totals, 12" pipe totals, etc.) 

Structure Report Includes:     Click Here for Structure Report

  1. Structure List for the entire utility take-off organized by structure description. Includes Structure Dimensions and Structure Height.
  2. Structure Excavation. Includes breakdown by strata for take-offs with borings.
  3. Structure Backfill. Totals of all backfill materials for structures.